€1 billion to replace fossil process heat in industry.
EU auction with €1 billion for new capacity that decarbonises industrial process heat through electrification, solar thermal or geothermal heat, or nuclear heat. A fixed premium per tonne of CO2 abated for 5 years, ranked on price, in three temperature topics from 80°C.
Until the official launch on 1 January 2027 we are making the final improvements. Our editors check every scheme, but details may still be incomplete or out of date. Check the official publication before you apply.
In brief
What is Innovation Fund Heat Auction?
Who
Projects located in the European Economic Area. There is no limitation on the origin or type of the consortium members, such as energy companies, project developers or industrial players.
New capacity producing industrial process heat with electrification technologies (heat pumps, direct and indirect resistance heating including thermal energy storage, electromagnetic and dielectric heating, plasma heating), solar thermal or geothermal heat, innovative nuclear heat, or hybrids of these, with at least 3 or 5 MWth and €2.5 million CAPEX. Electrolysis, electric arc furnaces for steel making, space heating and sale to district heating are not eligible.
A fixed premium for the CO2 abated by the heat produced, paid for 5 years after entry into operation. The maximum grant equals the subsidy requested per MWhth times the expected yearly heat volume times 5 years, up to €100 million per bid in the low and medium temperature topics and €250 million in the high temperature topic.
Bid the subsidy requested in EUR/MWhth with the nominal thermal capacity and the expected yearly heat volume, using the Funding and Tenders Portal forms. Add the financial information file, participant information, Gantt chart, feasibility study, permitting strategy and a bank's letter of intent for the completion guarantee. Bids are ranked on price in EUR/tCO2.
Built from the details on this page, with nothing added by us.
Max grant per strand
€100m – €250m
3 strands
Purpose & impact
Why does this scheme exist?
To reduce GHG emissions in industry by cost-effectively supporting the market uptake of electrified, direct-renewable and nuclear industrial process heat.
01
Cost-efficient support
An open competitive auction ranks bids on their price per tonne of CO2 abated; in the power sector, auctions brought down the support costs for renewable electricity by magnitudes.
02
Price discovery and market formation
With sufficient competition, the bids reveal the real cost of decarbonised process heat and create vetted price points where markets do not yet exist.
03
De-risking projects
A fixed premium on verified heat production for five years helps close the cost gap with fossil heat and leverages private capital.
04
Less grid pressure
A 25% bid bonus rewards energy storage, efficient heat pumps, direct renewable heat and nuclear heat, which lower electricity demand in peak hours.
Description
About the scheme
Compiled from passages of the scheme's official publication, with nothing added by us.
The Innovation Fund 2026 Heat Auction (IF26 Heat Auction) will be launched in December 2026 with a planned budget of €1 billion raised from the auctioning of EU Emissions Trading System (EU ETS) allowances.
Read moreRead less
The auction will support innovative technologies to decarbonise process heat from three main categories– electrified technologies such as heat pumps, thermal storages, plasma torches and electric boilers; direct renewable heat from solar thermal or geothermal; and for the first time nuclear technologies such as small modular reactors. Process heat refers to the energy used to generate medium and high temperatures for manufacturing activities in sectors such as chemicals, pulp & paper, steel, food & beverage or cement.
The second edition of the auction expands eligibility to include some projects using heat from as low as 80ºC and provides further incentive to implement flexibility solutions which reduce the pressure on the electricity system.
Successful bidders will receive a fixed premium subsidy that is linked and proportional to each tonne of direct CO2 emissions abated for a maximum period of five years.
Am I eligible?
Conditions
Quoted verbatim from the scheme, with the article that sets each condition.
01
Proposals must be for projects located in the EEA. There is no limitation on the origin or type (e.g. energy company, project developer, industrial player etc.) of members of the consortium.
Proposals must concern the deployment of industrial process heat: electrification technologies (e.g. heat pumps, direct and indirect resistance heating including thermal energy storage, electromagnetic and dielectric heating, plasma heating) or direct-renewable (solar thermal or geothermal) heat technologies, innovative nuclear technologies, including light water small modular reactors, advanced modular reactors, microreactors, and fusion (nuclear heat) or hybrid projects of the above-mentioned technologies.
Biomass or hydrogen use for heat production is not eligible (footnote 19).
Electrolysis processes (e.g. in the aluminium sector) are not eligible. Electric arc furnaces for steel making are not eligible. Heat production for space heating or sale to district heating is not eligible.
Heat production for activities primarily aimed at fuel production based on non-recycled fossil feedstocks is not eligible, excluding the production of low-carbon fuels.
Projects must not install new fossil fuel-fired capacity as part of the same installation as concerns the project.
Glass furnaces are exempt; other applications with similar technical or safety restrictions must provide evidence of these barriers and a transformation path to climate neutral fuel.
The electrified or direct-renewable process heat needs to be produced by new thermal capacity (i.e. heating production units for which at the time of application start of works did not yet take place), in order to ensure an incentive effect of the subsidy.
Grid connection requests, agreements or works, land purchase, permits and preliminary feasibility studies do not count as start of works (footnote 22).
A restriction on the maximum grant amount per bid applies: EUR 100 million in the low or medium temperature heat topic and EUR 250 million in the high temperature heat topic.
The newly installed capacity must be in a single location (several units can be combined together in a single location); virtual pooling of capacity is not permitted, but pooling capacity at a single physical site is permitted.
A low temperature heat topic that covers heat produced at a metered temperature of 80-100°C that have a size equal to or higher than 5 MWth and which utilise heat pumps with COP >1.5, direct renewables or nuclear heat. Other electrification technologies are not eligible for this topic.
Process heat below 80°C, 100°C or 400°C, depending on the topic, is not eligible.
Restrictions may be placed on sourcing inverters from high-risk countries if they are installed as part of the project and may supply electricity to the grid (e.g. battery energy storage systems).
This does not apply to inverters in technologies that do not supply electricity to the grid.
At application stage, subsidised heat production will be limited to the equivalent of 70% of hours per year at nominal capacity for all projects not claiming the ‘indirect emissions/flexibility’ bonus.
This is why there is a bid bonus of 25% (i.e. reduction of the bid price for the purpose of ranking only) for the projects that can prove: they deploy new electricity or thermal storage for the purpose of the project sufficient to replace the project’s electricity consumption from the grid or the heat demand of the process by 20%, for duration of 4h and active within 1h. Onsite or offsite storage is acceptable; or they deploy heat pump(s) with Coefficient of Performance (COP) of at least 1.5; or they deploy direct renewable heat or nuclear heat.
The bonus must be claimed at the bidding stage; failing to prove it at entry into operation may lead to termination and a call on the completion guarantee.
Ceiling price of 400 EUR/tCO2 proposed in the low and medium temperature topics. Ceiling price of 800 EUR/tCO2 proposed in the high temperature topic. Ceiling prices apply after bid bonuses have been applied.
Projects must comply with the applicable ‘Do No Significant Harm’ technical screening criteria outlined in Commission Delegated Regulations (EU) 2021/2139 (‘Climate Delegated Act’).
Relevance and quality (technical, financial and operational maturity) are assessed pass/fail.
A completion guarantee covering 6% of the maximum grant amount will be requested from projects invited to prepare grant agreement. A letter of intent from a bank or financial institution to issue a completion guarantee will be required as part of the proposal.
Issued by an EEA bank or financial institution rated at least BBB- (S&P/Fitch), Baa3 (Moody's) or BBB (low) (DBRS), within two months of the evaluation result letter.
Maximum time to reach FC from Grant Agreement signature: 2.5 years after signing the grant agreement. Maximum time to reach EiO from Grant Agreement signature: 5 years after signing the grant agreement.
At entry into operation at least 100% of the thermal capacity and eligible temperature levels stated in the bid must be operational.
Heat produced at a metered temperature of 80-100°C by projects of at least 5 MWth that use heat pumps with a COP above 1.5, direct renewables or nuclear heat; other electrification technologies are not eligible, and hybrids only when they combine these technologies. Topic budget €100 million; ceiling price €400 per tonne of CO2 after the bid bonus.
Maximum grant amount per bid €100 million: the subsidy requested per MWhth times the expected yearly heat volume times 5 years. Minimum project CAPEX €2.5 million.
Fixed premium per MWhth of heat produced; the bid in EUR/MWhth is converted into EUR/tCO2 with 0.224 tCO2/MWhth. No funding percentage.
Heat produced at a metered temperature of 100-400°C by projects of at least 3 MWth, with any eligible electrification, direct-renewable or nuclear heat technology. Topic budget €600 million; ceiling price €400 per tonne of CO2 after the bid bonus.
Maximum grant amount per bid €100 million: the subsidy requested per MWhth times the expected yearly heat volume times 5 years. Minimum project CAPEX €2.5 million.
Fixed premium per MWhth of heat produced; the bid in EUR/MWhth is converted into EUR/tCO2 with 0.224 tCO2/MWhth. No funding percentage.
Heat produced at a metered temperature above 400°C by projects of at least 3 MWth, with any eligible electrification, direct-renewable or nuclear heat technology. Topic budget €300 million; ceiling price €800 per tonne of CO2 after the bid bonus.
Maximum grant amount per bid €250 million: the subsidy requested per MWhth times the expected yearly heat volume times 5 years. Minimum project CAPEX €2.5 million.
Fixed premium per MWhth of heat produced; the bid in EUR/MWhth is converted into EUR/tCO2 with 0.224 tCO2/MWhth. No funding percentage.
Total scheme budget
€1bn · €1 billion from EU ETS revenues for the three topics; national budgets may be added via Auction-as-a-Service.
Budget status
Not published by the source
The sources do not say how much budget is left (checked 19 November 2026).
Combination with public support for the project's CAPEX or OPEX is not allowed, except for: previous support for early development stages (research, feasibility or FEED studies); previous support for capacity that is not part of the bid; indirect emission cost compensation under the ETS State aid Guidelines, under conditions; general and non-selective grid fee reductions not related to the project; demand side response and flexibility measures if the storage required by the auction is not remunerated as new capacity; support for non-dedicated energy infrastructure; and reductions of levies financing energy and environmental policy (allowed for the 2026 round). Not allowed: reductions of levies or taxes that reflect the cost of providing electricity, electricity price relief under section 4.5 of CISAF, and schemes supporting the same CO2 abatement. Support to equipment manufacturers, electricity installations and off-takers is allowed. A self-declaration is required.
Cycle: One-stage, pay-as-bid auction ranked on price. Indicative timeline: opening early December 2026, closing mid-February 2027, evaluation March to May 2027, results May to June 2027, grant agreement signature by November 2027 at the latest. Slide 'Application process – Indicative deadlines'; Table 3, points 3.1 and 3.3
Detailed budget table/calculator ('financial information file' with the bid calculation)
Participant information
Timetable/Gantt chart
Feasibility study
Permits, licences and authorisations strategy
Completion guarantee letter of intent (template is provided and is mandatory to use)
Equity supporting evidence
Equipment procurement supporting evidence
Heat off-taker supporting evidence (if relevant)
Electricity sourcing strategy
Heat off-taker strategy
Procedure
Proposals that pass admissibility and eligibility are ranked per topic by bid price in EUR/tCO2 after the bid bonus, from lowest to highest. Those whose maximum grant amounts fit the topic budget, plus a reserve list, are assessed pass/fail on relevance and quality, including DNSH; the others are rejected. Selected projects provide a completion guarantee of 6% of the maximum grant within two months, reach financial close within 2.5 years and entry into operation within 5 years of grant agreement signature, and are paid yearly (every 6 months on request for a consortium with an SME) on independently verified heat production.
Not the scheme's rules
Additional information
From the explanatory notes, FAQs, manuals or webinars on the scheme. This information is not legally binding; where it differs, the scheme's rules prevail.
Indicative timeline (DG CLIMA, national information webinars, October 2026): auction opening early December 2026, closing mid-February 2027, evaluation March to May 2027, results May to June 2027, latest grant agreement signature November 2027. According to CINEA (17 November 2026) the Commission plans to launch the call on 3 December 2026; the IF26 Heat Auction Info Day is on 9 December 2026, 14:30-17:30 CET.
Changes from IF25 (webinar): minimum temperature lowered from 100°C to 80°C for heat pump, nuclear heat or direct renewable installations of at least 5 MW; heat pumps may also use waste heat from nuclear power generation or data centres; nuclear heat added; fossil fuel refining no longer eligible unless for low-carbon fuels; minimum CAPEX of €2.5 million; possible limits on inverters from high-risk suppliers; all bids ranked with the natural gas emission factor instead of the fuel replaced; a 25% ranking bonus replaces the 70/80/100% run-hour tiers; 2.5 years to financial close and 5 years to entry into operation (IF25: 2 and 4); up to 140% production in a given year; grid connection works do not count as start of works; electric boilers metered at 100% efficiency (IF25: 95%); letters of intent for equity, equipment, off-takers and electricity supply replaced by evidence and strategies, while the completion guarantee letter of intent remains.
Also stated in the webinar: projects that have already been awarded funding under the Innovation Fund are ineligible, and only heat production for industry is eligible (not commercial, electricity generation or residential use).
Lessons learned from IF25 (webinar): do not edit the completion guarantee letter of intent template; choose as coordinator the company best able to pass the legal and financial checks; mind the strict prohibition of double funding from the EU budget; only claim the flexibility bonus when all conditions are clearly met, as penalties may apply; give a simple but clear justification when a heat pump uses waste heat; plan the metering of heat pump and MVR projects carefully; be aware of permitting issues for chemical thermal storage.
The webinar is non-binding: the call text and the FAQs on the Funding & Tenders Portal take precedence.